Case Study

A Multi-Purpose Marvel

By working together in the very early planning phases for the new Indiana Farm Bureau Fall Creek Pavilion, structural engineers and architects achieved a year-round, multi-purpose venue at Indiana’s state fairgrounds.

By Keven Shelley, AIA, LEED AP; Scott Clore, PE; and Michael Roach, PE

Seven years in the making and with $50 million from the Indiana General Assembly, the Indiana Farm Bureau (INFB) Fall Creek Pavilion opened in July 2023. The structure is a 196,000-square-footbuilding that caters to the State of Indiana with expanded possibilities, hosting events as varied as NCAA indoor track meets, large car auctions, and annual Indiana State Fair swine competitions. What sets this project apart is its versatility and the engineering achieved during challenging times such as the COVID-19 pandemic, supply chain disruptions, and the requirement to maintain the historic 1923 north façade.

Indiana Farm Bureau Fall Creek Pavilion, a historic red-brick event venue with arched windows and decorative masonry under a clear blue sky

The partnership between Schmidt Associate’s architects, Lynch, Harrison, and Brumleve, Inc., Complete Structural Consulting, Inc. engineers, and Indiana Bridge Fabricators was a multidisciplinary approach to collaboration and problem-solving. Despite the project’s scope, the team kept costs within the $50 million budget, and its strategic decisions resulted in over $1 million in savings.

Open-Web Joists

Coordinated Sourcing

Like any large project with multiple teams, the INFB Fall Creek Pavilion project faced challenges, notably the need to adapt to various uses. This required coordination and upfront research from stakeholders. The original joist span, planned at 116 feet, was extended to 212 feet during design development to accommodate program requirements to enable the Pavilion to host USA Track and Field events.

At the time of bidding this project, the production market for open web steel joists was at capacity, mainly due to the construction of warehouse facilities for online retailers such as Amazon. The limited supply for steel joists, especially 200-feet, three-piece, double-field-spliced super long spans, presented a significant problem. Allocating the necessary production time for a complex and demanding project made costs prohibitive for a traditional joist supplier. Realizing the need to keep the project on track, specialty engineer Complete Structural Consulting, Inc. was brought onboard so the joists could be produced by the steel fabricator using the specifications of a traditional Steel Joist Institute (SJI) supplier.

To achieve this goal, several design and fabrication procedures were documented and reviewed among the design team. A quality manual was developed by the specialty engineer and steel fabricator to document the shop standards instituted to ensure the SJI requirements were maintained. The clarity and thoroughness of the documentation provided the design team and the owner with peace of mind while allowing the project to continue. The tailored design solution ensured the joists and large trusses adhered to the standards of the SJI, the American Institute of Steel Construction (AISC), the American Welding Society (AWS), and the Society for Protective Coatings.

Collaborative Design

The structure presents a simple facade from below, concealing the robust engineering behind its construction. Early in the design process, it was decided to use the joists and girders on the primary grids as key elements in the Main Wind Force Resisting System (MWFRS). Incorporating the joists into the lateral system eliminated the need for diagonal bracing, thereby maximizing usable floor space. Close coordination between the designer of record and the specialty engineering team ensured that all structural members—the girders, joists, columns, and their respective connections—worked together to provide adequate resistance and a clear load path for all gravity and lateral loads.

Streamlined Construction

The consistent truss geometry also helped to streamline the construction process for the steel erector. This standardized design allowed for the development of repeatable methods in the splicing and erection of trusses, contributing to efficient and expedited completion. The long-span joists were delivered to the site in three separate pieces, then assembled in pairs on the ground before being lifted into their final position and bolted to supporting members. To ensure precise and consistent geometry, the erector built a large jig for assembling each three-piece joist on the ground.

Erecting the initial pair of trusses posed a challenge, requiring exact coordination to keep the first truss stable while positioning and bolting the second truss with bolted X-bracing to form a stable pair. The initial lift required four large cranes, with one crane stabilizing each half of the truss pair. Once the stable pair was erected and bolted, each subsequent truss could be individually erected and braced to the others with the bolted X-bridging. Once the roof deck was welded to the joists and provided lateral restraint for the top chords, the trusses were fully installed and ready for their full design loads.

The 200-foot joists were designed with a 2-inch chord gap to increase rigidity in the weak axis. This design provided more stability during erection and minimized the necessary bolted bridging. This design feature also allowed for larger single-member webs, resulting in fewer web members. The fabricator, using techniques common for SJI joist suppliers, crimped up to a 3-inch single-angle rather than using double angle sections. 2-inch HSS were also used as web members at critical locations and vertical web members. This approach provided more room at each panel point for aligning concentric members, as the single members are in the chord gap and the double angle webs are on the outside of the chords, resulting in less secondary bending, fewer double angle sections, and further enhancing the openness of the expansive area.

Unique Challenges and Solutions

The onset of the COVID-19 pandemic halted the project, with a rebid in 2021. While challenging, this delay provided the teams time to reassess and refine the project’s design and logistical plans that led to a more efficient outcome.

The project team also learned valuable lessons in flexibility and adaptation. An example was the work with the Indiana Bridge fabrication shop, which brought the project to life. This hands-on experience and the Owner’s involvement led to a smooth and transparent process, highlighting the importance of open communication. Permanent shoring on the north side of the building proved beneficial. The team initially proposed a temporary steel H-pile and wood lagging system, but the contractor proposed sheet metal piling for efficiency. As a result, even though more concrete was required due to the depth of the sheet piles that also served as formwork for the lower wall, the installation proceeded faster, helping to keep the project on schedule.

Historic Preservation

Preserving the historic street-level main entry structure on the north side of the building was identified early on as a critical aspect of the project. The existing street level was 10 feet higher in elevation than the exhibition floor, and connecting these two elevations while preserving the entry proved to be a significant challenge. Three options were discussed among the design team and construction manager: 1) building a concrete retaining wall; 2) temporary H-piles and wood lagging; and 3) steel sheet piling.

The sheet pile shoring option allowed construction of the new exhibit and administration areas without compromising integrity. This approach, which used an entire bay to protect the facade, blended new developments with historic preservation. As such, the historic north entry elements, including the entry portals, two restroom towers in the northeast and northwest corners, and office space, were preserved. The original brick masonry veneer on the north entry was restored by repointing joints and replacing damaged brick with colorful porcelain tile cornice, utilizing masonry maintenance guidelines from the National Park Service. The decision to restore the north entry required that the entire Pavilion be constructed with a closely matched brick. The design team was able to find a suitable brick, seamlessly connecting the new construction to the original look. The design team also integrated restored and reclaimed wood from the original structure’s roof deck into the arched ceilings from the original Swine Barn’s three north entry portals .

Winning With Close Partnership

The INFB Fall Creek Pavilion is a win for Indianapolis and the State of Indiana due to its ongoing annual economic impact of over $200 million and the vitality to various sectors, from hospitality and transportation to local businesses and job creation. In its short life, the Pavilion has not only enhanced the capacity of the campus, but it also shows how challenges can become opportunities.